Sinara Development Puts Up Yekaterinburg Arena Ahead of Schedule
14 October 2016 (13:26)
UrBC, Yekaterinburg, October 14, 2016. Sinara Development came up with a performance report on the first year of its Yekaterinburg Arena Construction Project, Sinara Group’s press service reports.
The general contractor for re-building Yekaterinburg Central Stadium in time for the world football championship of 2018 by now had the roof pylons and supports completed, the inner roof ring assembled, and all the concrete frames for the northern and southern spectator stands installed.
Builders are currently working on the outer roof ring, putting up the western and the eastern spectator stands, and installing metal frames for the temporary stands in the northern and southern sections of the stadium. They are also installing the heating infrastructure under the stands.
Besides, five security checkpoints and an entrance are expected to be ready by the end of the year.
The stadium will get commissioned in December 2017, in full compliance with the terms of the contract Sinara signed with the Russian Government.
The general contractor for re-building Yekaterinburg Central Stadium in time for the world football championship of 2018 by now had the roof pylons and supports completed, the inner roof ring assembled, and all the concrete frames for the northern and southern spectator stands installed.
Builders are currently working on the outer roof ring, putting up the western and the eastern spectator stands, and installing metal frames for the temporary stands in the northern and southern sections of the stadium. They are also installing the heating infrastructure under the stands.
Besides, five security checkpoints and an entrance are expected to be ready by the end of the year.
The stadium will get commissioned in December 2017, in full compliance with the terms of the contract Sinara signed with the Russian Government.