EVRAZ ZSMK Invests RUB 90m in Converter Overhaul

28 November 2019 (09:28)

UrBC, Yekaterinburg, November 28, 2019. The 55-day overhaul of an oxygen converter (capacity: 100,000,000+ kg of steel a month) has been completed at EVRAZ Holding West-Siberian Integrated Metallurgical Plant (EVRAZ ZSMK); the plant has invested RUB 90m into the project.

‘The overhaul involved replacing the primary and ancillary parts of the converters as well as installing a new control and operation system. This will improve the steel-smelters’ working conditions and will ensure the converter unit’s uninterrupted performance,’ says EVRAZ PR Department.

The plant currently operates five converters all in all, with total steel output at 570,000,000 kg a month. Another converter, as well as a CC machine, are scheduled for an overhaul in 2020; Oxygen Converter 4 will get fully replaced next year also.

EVRAZ ZSMK’s steel-smelting facilities produce around 35 different kinds of steel with the help of slab-casting and sorting CC machines. The billets either get used for making rolled metal goods or get exported. The slabs manufactured at the plant get supplied to 20 different countries.


Other materials on the topic::