Akademicheskaya Power Station Almost Complete in Yekaterinburg
1 June 2016 (17:53)
UrBC, Yekaterinburg, June 1, 2016. The construction of the 230-megawatt Akademicheskaya Power Station is almost complete, T Plus Sverdlovsk division’s press service reports.
For one, power supply has already been provided for the power start-up of the 110-kilowatt gas-insulated switch gear and a program has been activated for the start-up of the auxiliary transformer for balance-of-plant needs and voltage supply onto 6-kilowatt sections.
The water treatment plant was launched the other day, which means the power station will now have a supply of desalinated water needed for the boiler feeding. Also, the gas turbine has been prepared for its initial firing on May 28.
Following the start-up and commissioning jobs and the launch of the combined cycle gas turbine, the station will be ready to start producing electric power in July 2016.
For one, power supply has already been provided for the power start-up of the 110-kilowatt gas-insulated switch gear and a program has been activated for the start-up of the auxiliary transformer for balance-of-plant needs and voltage supply onto 6-kilowatt sections.
The water treatment plant was launched the other day, which means the power station will now have a supply of desalinated water needed for the boiler feeding. Also, the gas turbine has been prepared for its initial firing on May 28.
Following the start-up and commissioning jobs and the launch of the combined cycle gas turbine, the station will be ready to start producing electric power in July 2016.