We’ll set up new units that will let us produce 800 megawatt within five years, says Managing Director of local generating company Leonid Chetverkin
31 January 2006 (11:30)
‘We are going to introduce some new units that will allow us to produce 800 megawatt and, moreover, combine the production of thermal energy with electricity which will, in its turn, lead to a smaller prime cost,’ Leonid Chetverkin, Managing Director of the local subsidiary of TGK-9 JSC, generating company, announced at today’s press conference.
According to Mr Chetverkin, TGK-9 is producing plenty of energy now. During the cold weather week, for example, the company had been producing 1,000 megawatt more than was actually needed for Sverdlovsk region, so 1,700 megawatt of extras was given to the other regions.
‘Even though we had to sue more expensive fuels in December, we still produced 6% more of electricity and 15% more of heat, so the company might actually make more profits than elsewhen,’ Mr Chetverkin said.
‘Yet we still have to maintain the equipment, and we had 4,500 kilometers of lines repaired in 2005. The same is going to be fixed in 2006, though in the best of all possible worlds, 10,000 kilometers of lines should be taken care of annually,’ Mr Chetverkin noted.
According to Mr Chetverkin, TGK-9 is producing plenty of energy now. During the cold weather week, for example, the company had been producing 1,000 megawatt more than was actually needed for Sverdlovsk region, so 1,700 megawatt of extras was given to the other regions.
‘Even though we had to sue more expensive fuels in December, we still produced 6% more of electricity and 15% more of heat, so the company might actually make more profits than elsewhen,’ Mr Chetverkin said.
‘Yet we still have to maintain the equipment, and we had 4,500 kilometers of lines repaired in 2005. The same is going to be fixed in 2006, though in the best of all possible worlds, 10,000 kilometers of lines should be taken care of annually,’ Mr Chetverkin noted.
Embed to Blog | Subscribe to Newsletter |
Other materials on the topic::
- Yekaterinburgnefteprodukt’s gas stations suffer from fuel shortage
- IES Multiutilities gets new executive
- Ural Turbine Works presents Reconstruction of Cogeneration Plant-12 Project on May 26
- Experts of Ural Turbine Works take part in presentation of Heat Power Plant No 12 Reconstruction Project by Solikamskbumprom JSC on May 26, 2006
- Electricity network load goes up from 790 megawatt to 908 megawatt, reports local supplier