Главная > Daily news > Beloyarskaya power plant preparing to start BN-600 power-generating unit
Beloyarskaya power plant preparing to start BN-600 power-generating unit22.05.2006 |
Beloyarskaya power plant is completing the scheduled equipment inspection and preparing to start the BN-600 power-generating unit. The unit was shut down on March 24, 2006 in order to carry the inspection out and to get the unit refueled. Since then, the reactor of BN-600 was refueled and one of its six sodium-sodium heat exchangers was replaced in order to investigate it within the framework of the Program for Support of Extension of BN-600 Projected Service Life. The scheduled routine maintenance operations, including installation of a modern field system at the electric generator No. 4, overhaul of the turbine No. 5 and the electric generator No. 6 were accomplished as well. The start of BN-600 is scheduled for May 21, 2006. Then the power unit is expected to reach its rated power level gradually, within one or two days. Вернуться назад |