Nickel producer of Ufaley carries out repair of pipe furnace № 1
22 February 2006 (09:16)
The repair of pipe furnace № 1 is currently carried out at the burning shop of Ufaleynickel JSC, regional nickel maker.
As the company’s spokesperson said to UrBC representative, the repair will provide for the uninterrupted and efficient performance of the furnace and will also help prevent emergency shutdowns.
The repair works will include replacement of lining, bunker, and fire-resistant segments. After the completion of these, the furnace will be immediately put into operation.
As the company’s spokesperson said to UrBC representative, the repair will provide for the uninterrupted and efficient performance of the furnace and will also help prevent emergency shutdowns.
The repair works will include replacement of lining, bunker, and fire-resistant segments. After the completion of these, the furnace will be immediately put into operation.
Embed to Blog | Subscribe to Newsletter |
Other materials on the topic::
- Magnesite Group Ltd. carries out experimental-industrial operations on blast furnace lining for Ufaleynickel JSC
- Ufaleynickel repairs its direct current furnace
- Ufaleynickel JSC assembles and puts into operation new shifting chute
- Nickel maker of Ufaley does scheduled repair of SBZ-1 furnace
- Nickel Producer of Ufaley repairs converter