Investigative Committee: Copper-Smelting Furnace at Sredneuralsky Plant Partially Destroyed

A criminal lawsuit is now being processed in Sverdlovsk Region, with charges of labor safety violations resulting in a man’s death. The accident occurred at Sredneuralsky Copper-Smelting Plant’s copper-smelting shop at 11:30 PM on August 7, 2011. The copper-smelting furnace was partially destroyed due to violations of the technological procedures, and some molten metal burst out, leaving a forty-nine-year-old dust – and gas-trapping unit operator with severe thermal burns; shortly after, the worker died at the scene of the accident. What is more, some thirty-five-year old furnace operators
09 August 201111:13

UMMC: Culprits at Sredneuralsky Copper-Smelting Plant to Be Determined in Two Weeks

An ad hoc committee is now looking into the accident that left one worker killed by an outburst of motel metal out of a copper-smelting furnace, UMMC Holding’s press service reports. The final conclusions as to what caused the tragedy and who is to blame can be made no sooner than in two weeks’ time, after the ad hoc committee completes its work. To detect the causes of the accident and to give its evaluation, the copper-smelting shop was halted, while all the other plant departments keep operating as usual.
09 August 201111:13

300 Companies to Take Part in RussianExpoArms 2011

About three hundred Russian and foreign enterprises confirmed their intention to take part in RussianExpoArms 2011, Concern Sozvezdiye, Tactical Missiles Corporation JSC, Concern PVO Almaz-Antey, Military Industrial Company, Oboronservice, and KAMAZ among them. A number of installations will be presented at the exhibition, including some demonstrations of full-scale specimens manufactured by a few foreign companies, for example, by Iveco Defense Vehicles, Renault Trucks Defense, and Nexter. Besides, France, Ukraine, and Byelorussia will provide their unified ‘by-country’ show rooms.
09 August 201111:13

Karabashmed Keeps Undergoing Upgrades

A contract was signed recently between Karabashmed and the German Linde AG Gas and Engineering for the delivery of two blocks of an oxygen plant with the total capacity of 10,000 cubic nanometers of process oxygen per hour. The implementation of this contract is part of a reconstruction program for Karabashmed’s chemical and metallurgical facility that will allow not only for more copper concentrate to be recycled with the help of Ausmelt furnace but also for larger-scale recycling of the harmful production waste. The launch of the new vitriolic shop, expected in December 2013, will ensure