Sinara Development Assembles Yekaterinburg EXPO Congress Center
30 August 2017 (16:30)
UrBC, Yekaterinburg, August 30, 2017. Sinara Group’s Sinara Development started assembling the framework of Yekaterinburg EXPO Congress Center, the Group’s PR Center reports.
According to Sinara Development’s Director-General Timur Ufimtsev, the assembly can get done quickly and efficiently thanks to using a metal frame and reinforced concrete plates. This will also ensure the building’s excellent operational properties.
‘The framework is expected to be finished in early spring of 2018. The entire structure will weigh around 5,000,000 kg,’ Ufimtsev said.
The workers are currently busy finishing the pile field and laying the reinforced concrete foundation pieces. 700 piles out of 2,500 are already in place, with 350 m3 of concrete poured over.
Sinara Development is putting up this Congress Center as part of its contract with Ural Exhibition Center. Under the terms of their agreement, the building is to be commissioned in June 2019.
According to Sinara Development’s Director-General Timur Ufimtsev, the assembly can get done quickly and efficiently thanks to using a metal frame and reinforced concrete plates. This will also ensure the building’s excellent operational properties.
‘The framework is expected to be finished in early spring of 2018. The entire structure will weigh around 5,000,000 kg,’ Ufimtsev said.
The workers are currently busy finishing the pile field and laying the reinforced concrete foundation pieces. 700 piles out of 2,500 are already in place, with 350 m3 of concrete poured over.
Sinara Development is putting up this Congress Center as part of its contract with Ural Exhibition Center. Under the terms of their agreement, the building is to be commissioned in June 2019.